Published by Electrotek Concepts, Inc., PQSoft Case Study: Substation Voltage Flicker Data Analysis, Document ID: PQS1208, Date: June 4, 2012.
Abstract: This case study presents a substation arc furnace flicker measurement data evaluation. The characteristics of voltage flicker are mainly determined by load characteristics and the short-circuit capacity. The analysis included a helpful index for comparing voltage flicker measured at a source and at a remote substation. The measurement results showed that the three-phase voltage flicker Pst measured at the 138kV Steel Mill Substation and the three other substations exceeded the CP99 compatibility limit. Mitigation alternatives for excessive voltage flicker may include a synchronous compensator (STATCOM).
SUBSTATION VOLTAGE FLICKER DATA ANALYSIS CASE STUDY
A substation arc furnace voltage flicker measurement data evaluation case study was completed for the system shown in Figure 1. Voltage flicker is a power quality problem caused by large time-varying loads like electric arc furnaces. The steel mill facility included an arc furnace and STATCOM supplied from a utility substation that included one 80 MVA, 138kV/13.8kV transformer. A static synchronous compensator (STATCOM) is a regulating device based on a power-electronic voltage-source converter that can act as either a source or sink of reactive power and therefore be used for mitigating voltage flicker.
The monitoring period was from May 21, 2010 thru November 4, 2010. The power quality instruments used to complete the voltage flicker and power quality measurements were the Dranetz Encore SeriesTM and Dranetz PowerXplorer PX5. The instruments sample voltage and current at 256 points-per-cycle, and follow the IEC 61000-4-15 method for characterizing voltage flicker data. The sampling rate also allows characterization of low to-medium frequency oscillatory transients and harmonics thru the 63rd. The measurement and statistical analysis was completed using the PQView® program.
Figure 1 – Illustration of Oneline Diagram for Substation Voltage Flicker Data Evaluation
Any load that has important time variations, especially in the reactive component, can cause voltage flicker. The term flicker is derived from the impact of varying voltage magnitudes on lighting intensity. Loads that can exhibit continuous, rapid variations in the load current magnitude can cause voltage variations referred to as flicker. Arc furnaces are the most common cause of voltage flicker on utility transmission and distribution systems. Other sources of voltage flicker include motor starting, welders, rolling mill drives, main winders, electric saws and hammers, cranes, and elevators. In general, loads with a high rate-of-change of power with respect to the short-circuit capacity at the point of connection are all possible sources of voltage flicker.
The envelope of the 60 Hz variations is defined as the flicker signal, Vf, and its rms magnitude is expressed as a percent of the fundamental. Voltage flicker appears as a modulation of the fundamental frequency (similar to amplitude modulation of an am radio signal). Therefore, it is easiest to define a magnitude for voltage flicker as the rms magnitude of the modulation signal. This can be obtained by demodulating the waveform to remove the fundamental frequency and then measuring the magnitude of the modulation components. A magnitude that is as low as 0.5% can sometimes result in perceptible light flicker if the frequencies are in the range of 1-5 Hz.
Voltage flicker is measured with respect to sensitivity of the human eye. IEC 61000-4-15 defines the methodology and specifications of instrumentation for measuring voltage flicker. This standard includes a method for describing the potential for visible light flicker through voltage measurements. The measurement method simulates the lamp/eye/brain transfer function and produces a fundamental metric called short-term flicker sensation (Pst). This value is normalized to 1.0 to represent the level of voltage fluctuations sufficient to cause noticeable flicker to 50 percent of a sample observing group. Another measure called long-term flicker sensation (Plt) is sometimes used for verifying compliance with compatibility levels established by standards bodies and used in utility power contracts. This value is a longer-term average of Pst samples.
Figure 2 shows a representative voltage and current waveform measured at the point of common coupling (PCC) 138kV transformer primary in the Steel Mill Substation. The fundamental frequency phase-to-ground voltage was 81.657kV (1.03 per-unit), the rms voltage was 81.703kV, and the total harmonic voltage distortion (VTHD) was 1.86%. The fundamental frequency current was 208.8 A, the rms current was 251.7 A, and the current distortion (ITHD) was 33.16%.
Figure 2 – Steel Mill Substation Representative Voltage and Current Waveforms
IEEE Std. 1453 and IEC 61000-2-2 include specifications for measurement of voltage flicker and recommended compatibility levels. The standards recommend a compatibility level of Pst=1.0 for power systems met by 99% of the measured values (CP99). Figure 3 shows the three-phase voltage flicker Pst histogram measured at the 138kV Steel Mill Substation for the entire monitoring period. Statistical analysis of the 66,486 individual steady-state measurements yielded a CP50 value of 0.97, a CP95 value of 1.90, and a CP99 value of 2.19. The results show that the CP99 compatibility limit of 1.0 is exceeded. Note that CP95 refers to the cumulative probability, 95th percentile of a value.
Figure 3 – Steel Mill Substation Histogram of Voltage Flicker Values
A useful index for comparing voltage flicker measured at a source and at a remote substation is the “flicker transfer factor”. The flicker transfer factor is the ratio of the voltage flicker measured at the remote bus against the flicker at the source:
TPstAB = PstB / PstA
A voltage flicker transfer factor of 1.0 would mean that the remote substation bus has the same amount of voltage flicker as produced by the source of the disturbance; while a flicker transfer factor of 0.5 means that the remote substation bus sees the flicker diminished by half the value. Typically, flicker transfer factors are less than 1.0 because network impedances and generation sources tend to stiffen the system, while distribution loads also tend to lessen the effect.
Figure 4 shows the three-phase voltage flicker Pst histograms measured at the 138kV Steel Mill Substation and at Substation #2. The results for the Steel Mill Substation included a CP50 of 0.75, a CP95 value of 1.69, and a CP99 value of 1.95. The results for Substation #2 included a CP50 of 0.56, a CP95 value of 1.26, and a CP99 value of 1.47.
Figure 4 – Steel Mill Substation and Substation 2 Voltage Flicker Values
The voltage flicker transfer factors for Substation #2 include:
Location
CP50
CP95
CP99
Steel Mill Substation
0.75
1.69
1.95
Substation #2
0.56
1.26
1.47
Flicker Transfer Factor
0.75
0.75
0.75
The CP99 flicker transfer factor of 0.75 indicates that Substation #2 sees 75% of the flicker produced by the arc furnace at the Steel Mill Substation.
Figure 5 shows the three-phase voltage flicker Pst histograms measured at the 138kV Steel Mill Substation and at Substation #3. The results for the Steel Mill Substation included a CP50 of 1.12, a CP95 value of 2.01, and a CP99 value of 2.33. The results for Substation #3 included a CP50 of 0.85, a CP95 value of 1.53, and a CP99 value of 1.81.
Figure 5 – Steel Mill Substation and Substation 3 Voltage Flicker Values
The voltage flicker transfer factors for Substation #3 include:
Location
CP50
CP95
CP99
Steel Mill Substation
1.12
2.01
2.33
Substation #3
0.85
1.53
1.81
Flicker Transfer Factor
0.76
0.76
0.78
The CP99 flicker transfer factor of 0.78 indicates that Substation #3 sees 78% of the flicker produced by the arc furnace at the Steel Mill Substation.
Figure 6 shows the three-phase voltage flicker Pst histograms measured at the 138kV Steel Mill Substation and at Substation #1. The results for the Steel Mill Substation included a CP50 of 1.06, a CP95 value of 2.03, and a CP99 value of 2.29. The results for Substation #1 included a CP50 of 0.56, a CP95 value of 1.05, and a CP99 value of 1.21.
Figure 6 – Steel Mill Substation and Substation 1 Voltage Flicker Values
The voltage flicker transfer factors for Substation #1 include:
Location
CP50
CP95
CP99
Steel Mill Substation
1.06
2.03
2.29
Substation #1
0.56
1.05
1.21
Flicker Transfer Factor
0.53
0.52
0.53
The CP99 flicker transfer factor of 0.78 indicates that Substation #1 sees 53% of the flicker produced by the arc furnace at the Steel Mill Substation.
Table 1 shows a summary of relevant terms and indices related to power quality problems on utility and customer power systems.
Table 1 – Power Quality Related Equations and Indices
SUMMARY
This case study summarized a substation arc furnace flicker measurement data evaluation. The characteristics of voltage flicker are mainly determined by load characteristics and the short-circuit capacity.
The analysis included a helpful index for comparing voltage flicker measured at a source and at a remote substation. Flicker transfer factor is the ratio of the voltage flicker measured at the remote bus against the flicker at the source bus. Flicker transfer factors are often less than 1.0 because network impedances and generation sources tend to stiffen the system, while distribution loads also tend to lessen the effect.
The measurement results showed that the three-phase voltage flicker Pst measured at the 138kV Steel Mill Substation and the three other substations exceeded the CP99 compatibility limit. Mitigation alternatives for excessive voltage flicker may include a synchronous compensator (STATCOM).
REFERENCES
IEEE Recommended Practice for Measurement and Limits of Voltage Fluctuations and Associated Light Flicker on AC Power Systems, IEEE Std. 1453-2004, IEEE, 2005, ISBN: 0- 7381-4482-7.
IEEE Recommended Practice for Monitoring Electric Power Quality, IEEE Std. 1159-1995, IEEE, October 1995, ISBN: 1-55937-549-3.
IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems, IEEE Std. 519-1992, IEEE, ISBN: 1-5593-7239-7.
RELATED STANDARDS IEEE Std. 1453
GLOSSARY AND ACRONYMS DFT: Discreet Fourier Transform PCC: Point of Common Coupling TDD: Total Demand Distortion THD: Total Harmonic Distortion
Published by CEA Technologies Inc. (CEATI), POWER QUALITY Energy Efficiency Reference Guide, Chapter 2 – Understanding Power Quality Concepts.
2.1 The Electrical Distribution System
One of the keys to understanding power quality is to understand how electrical power arrives at the socket, and why distribution is such a critical issue.
Electrical power is derived from generation stations that convert another form of energy (coal, nuclear, oil, gas, water motion, wind power, etc.) to electricity. From the generator, the electricity is transmitted over long distances at high voltage through the bulk transmission system.
Power is taken from the bulk transmission system and is transmitted regionally via the regional supply system. Power is distributed locally through the distribution system and local utilities. The voltage of the distribution system is reduced to the appropriate level and supplied to the customer’s service entrance.
Figure 3: Electrical Transmission and Distribution
2.1.1 Voltage Levels and Configurations
The power supplied to the customer by the utility will be either single-phase or three phase power. Single-phase power is usually supplied to residences, farms, small office and small commercial buildings. The typical voltage level for single-phase power is 120/240 V (volts).
Figure 4: 120/240 V Single-phase Service
Three-phase power is usually supplied to large farms, as well as commercial and industrial customers.
Figure 5: Typical 208 V Three-phase Wye Connected Service
Typical voltage levels for three phase power supply are 120 V/208 V, 277 V/480 V (in the United States and Canada) or 347 V/600 V (in Canada).
Rotating equipment such as large motors and other large equipment require three-phase power to operate, but many loads require only single-phase power. Single-phase power is obtained from a three-phase system by connecting the load between two phases or from one phase to a neutral conductor.
Different connection schemes result in different voltage levels being obtained.
Figure 6: Grounded Wye Connection
2.1.2 Site Distribution
Electrical power enters the customer’s premises via the service entrance and then passes through the billing meter to the panel board (also referred to as the “fuse box”, “breaker panel”, etc.). In most residential or commercial installations electrical circuits will be run from this panel board.
Figure 7: Typical Residential Service
In larger distribution systems this power panel board will supply other panel boards which, in turn, supply circuits.
Figure 8: Service with Branch Panel Boards
A transformer is used if a different voltage or isolation from the rest of the distribution system is required. The transformer effectively creates a new power supply system (called a separately derived power source) and a new grounding point on the neutral.
Figure 9: Typical Transformer Installation
2.2 Basic Power Quality Concepts
2.2.1 Grounding and Bonding
Grounding
Grounding is one of the most important aspects of an electrical distribution system but often the least understood. Your Electrical Code sets out the legal requirements in your jurisdiction for safety standards in electrical installations. For instance, the Code may specify requirements in the following areas:
(a) The protection of life from the danger of electric shock, and property from damage by bonding to ground non-current carrying metal systems; (b) The limiting of voltage on a circuit when exposed to higher voltages than that for which it is designed; (c) The limiting of ac circuit voltage-to-ground to a fixed level on interior wiring systems; (d) Instructions for facilitating the operation of electricalapparatus (e) Limits to the voltage on a circuit that is exposed to lightning.
In order to serve Code requirements, effective grounding that systematically connects the electrical system and its loads to earth is required.
Connecting to earth provides protection to the electrical system and equipment from superimposed voltages from lightning and contact with higher voltage systems. Limiting over voltage with respect to the earth during system faults and upsets provides for a more predictable and safer electrical system. The earth ground also helps prevent the build-up of potentially dangerous static charge in a facility.
The grounding electrode is most commonly a continuous electrically conductive underground water pipe running from the premises. Where this is not available the Electrical Codes describe other acceptable grounding electrodes.
Grounding resistances as low as reasonably achievable will reduce voltage rise during system upsets and therefore provide improved protection to personnel that may be in the vicinity.
Connection of the electrical distribution system to the grounding electrode occurs at the service entrance. The neutral of the distribution system is connected to ground at the service entrance. The neutral and ground are also connected together at the secondary of transformers in the distribution system. Connection of the neutral and ground wires at any other points in the system, either intentionally or unintentionally, is both unsafe (i.e., it is an Electrical Code violation) and a power quality problem.
Equipment Bonding
Equipment bonding effectively interconnects all non-current carrying conductive surfaces such as equipment enclosures, raceways and conduits to the system ground. The purpose of equipment bonding is:
1) To minimize voltages on electrical equipment, thus providing protection from shock and electrocution to personnel that may contact the equipment. 2) To provide a low impedance path of ample current-carrying capability to ensure the rapid operation of over-current devices under fault conditions.
Figure 10: Equipment without Proper Equipment Bonding
Figure 11: Equipment with Proper Equipment Bonding
If the equipment were properly bonded and grounded the equipment enclosure would present no shock hazard and the ground fault current would effectively operate the over current device.
Published by Electrotek Concepts, Inc., PQSoft Case Study: Voltage Notching and Distribution Systems II – Large DC Drive Examples, Document ID: PQS0506, Date: June 30, 2005.
Abstract: This case study describes voltage notching associated with large DC drives. The notching is a normal characteristic of a phase-controlled rectifier but this paper illustrates problems that can occur on systems with low short circuit levels where the voltage notching can excite the natural frequency of the distribution system and cause significant distortion in the supply voltage. The notching characteristics and the interaction with the distribution system frequency response characteristics are described, along with possible solutions, An example problem and the corresponding solution associated with a large DC drive is presented.
INTRODUCTION
Adjustable speed ac and dc drives are used with very large motors (e.g. 1,000-20,000 hp) for a variety of reasons. The drives can result in significantly improved efficiency when the driven load is variable. For large motor applications on weak systems, the drives may be required for motor starting to avoid high inrush currents.
Adjustable speed ac drives (ASDs) 1000 hp and larger typically use phase-controlled rectifiers (SCRs) and a large dc link inductor to supply a relatively constant dc current to the inverter. This is known as a current source inverter (CSI) configuration. The input rectifier may be configured as a six pulse, twelve pulse, or even higher pulse number rectifier, depending on harmonic control requirements. For dc drive applications, phase-controlled rectifiers are used to supply the dc current directly to the dc motor.
The voltage notching discussed in this paper is caused by the commutating action of the controlled rectifier. Whenever the current is commutated from one phase to another, there is a momentary phase-to-phase short circuit through the rectifier switching devices (SCRs, in this case). For a six pulse converter, this happens six times each cycle. The voltage notch is defined by its duration and its depth. The duration (commutation period) is determined by the source inductance to the drive and the current magnitude. The depth of the notch is reduced by inductance between the observation point and the drive (e.g. isolation transformer or choke inductance). An example waveform illustrating simple notches resulting from a drive operation is shown in Figure 1.
Figure 1 – Example of voltage notches caused by converter commutation
PROBLEM DESCRIPTION
On most systems, problems with voltage notching can be minimized by applying sufficient isolation reactance at the drive. This limits the notch magnitude on the source side of the isolation reactance. However, on some systems, the notches that appear at the system level can still be significant. If there is not much resistive load on a system like this, the notches can excite the natural frequency of the distribution system (determined by the capacitance of lines, cables, and capacitor banks in parallel with the system source inductance) and cause significant distortion in the voltage waveform.
Numerous papers have described the voltage notching phenomena in industrial facilities and sizing isolation reactance to limit the notching effect on other loads [1-5]. However, there has been little literature describing the potential for voltage notching to excite natural frequencies of the distribution system. The high frequency oscillations that result can cause problems with communication interference and sensitive customer loads. This paper describes the concern and possible solutions using an example where a problems was encountered. The methodology for evaluating these problems and the solutions implemented should be valuable to anyone else encountering this problem.
It is important to note that the notching problem described should only exist with large adjustable speed drives with current-source inverter configurations or with dc drives. With other types of ASDs that use voltage source inverters (e.g. pulse width modulation), the rectifier does not have a constant dc current that needs to be commutated from one switching device to another. It is this current being commutated that that essentially looks like an injection of a disturbing current into the distribution system.
LARGE DC DRIVE APPLICATION
This example involves large dc drives used to pump a slurry in an industrial process. There are three sets of tandem 1000 hp dc drives used in the process. Initially, this customer was the only customer on the distribution system. Then, the distribution system was extended to supply a new customer with electronic controls for large gas turbine-driven compressors. When this new customer came on line, numerous problems were encountered, including motor heating and failures of control circuits. A one line diagram illustrating the system configuration is provided in Figure 2.
Measurements on the system indicated that harmonic distortion levels were unacceptably high on the 34.5kV system due to the operation of the dc drives. As a first step to try and solve the problem, the customer replaced the existing transformers supplying the dc drives with new transformers that had phase shifts designed to achieve 18 pulse operation for the overall facility (0 degrees, plus 20 degrees, and minus 20 degrees for the three transformers). This was effective in reducing the lower order harmonic components (when all three drives were operating) but it did not reduce the high frequency oscillation that was occurring as a result of a system resonance near the 35th harmonic. Figure 3 gives a measured waveform and spectrum from the 34.5kV system after the phase shifting transformers were put in service. Note that the distortion is spread over a range of harmonic components because the oscillation is not an exact multiple of 60 Hz. The corresponding voltage from the 480 volt service entrance at the new customer is given in Figure 4.
Figure 2 – Oneline diagram for the example system
Figure 3 – Measured voltage on 34.5kV system after installation of phase shifting transformers
Figure 4 – Voltage from 480 volt service entrance at new customer after installation of phase shifting transformers
Effect of 34.5kV Capacitor Bank
The best solution to eliminate the high frequency oscillations that are excited by notching from the dc drives is to change the frequency response of the distribution system. This is most easily done by adding a shunt capacitor bank at the 34.5kV level. Figure 5 gives the base case frequency response characteristic showing a resonance near the 35th harmonic, along with the response for three different capacitor sizes added to the 34.5kV system near the customer with the dc drives.
At this facility, the dc drives are not always operated together. During lighter load pumping requirements, there may only be one or two of the tandem dc drives in service. During these conditions, cancellation of the lower order harmonic current components is not achieved and resonances at the 5th, 7th, 11th, or 13th harmonics could be excited. For this reason, it is important that the capacitor addition at the 34.5kV level not cause a resonance near one of these characteristic harmonics.
Figure 5 – Effect of 34.5kV Capacitors on the System Frequency Response Characteristics
Figure 6 – Distortion profiles at the new customer service entrance with 900 kVAr feeder capacitor in service
A capacitor size of 900 kVAr was selected because it results in a resonance between the 7th and 11th harmonics (see Figure 5). This capacitor is most effective when the drives are operating in the full three pump mode and there is cancellation of the lower order harmonics. When in the two pump mode, generation of lower order harmonics increases the distortion on the system but the total harmonic distortion is still less than 5%. Plots of typical profiles of the total harmonic distortion, 7th harmonic component, and 8th harmonic component over a 24 hour period are shown in Figure 6. Note that the total harmonic distortion is normally less than 4%.
With this configuration, the new customer has been able to operate without problems. However, a better long term solution would involve the addition of 5th, 7th, and 11th harmonic filters at the 4.16 kV bus supplying the dc drives. These filters would prevent resonance problems at the low order harmonics during two pump operation, even if system changes in the future (e.g. another capacitor bank added to the distribution system or at a customer location) change the 34.5kV system frequency response characteristics.
SUMMARY
The paper illustrates the characteristics of high frequency oscillations that can result from the commutation notches of large adjustable speed ac or dc drives operating on systems with relatively low short circuit levels.
The system oscillations can be magnified at customer locations where low voltage capacitors exist. Small capacitors, such as motor surge capacitors can be a particular problem. Even capacitors in the power supplies for electronic loads or smaller adjustable speed drive rectifiers can be affected by these oscillations.
The problem can be solved by careful selection of a capacitor size for the primary distribution system. The capacitor should not introduce a new resonance at one of the characteristic harmonics of the adjustable speed drive. The interaction of the proposed capacitor with other system capacitors and harmonic filters must be evaluated.
REFERENCES
IEEE Std. 519-1992, IEEE Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems, IEEE, New York, 1993.
J.C. Read, “The Calculation of Rectifier and Converter Performance Characteristics,” Journal of the IEE, vol. 92, pt. II, 1945, pp 495-509.
E.F. Christensen, et. al., “Analysis of Rectifier Circuits,” AIEE Transactions, vol. 63, 1944, pp. 1048-1058.
R.A. Adams, et. al., “Power Quality Issues Within Modern Industrial Facilities, “IAS Textile Film and Fiber Meeting, Atlanta, GA., 1990.
D.A. Jarc and R.G. Schieman, “Powerline Considerations for Variable Frequency Drives, “IEEE Transactions on IAS, vol. 1A-21, no. 5, 1985.
RELATED STANDARDS IEEE Std. 519
GLOSSARY AND ACRONYMS ASD: Adjustable Speed Drive CSI: Current Source Inverter
Published by CEA Technologies Inc. (CEATI), POWER QUALITY Energy Efficiency Reference Guide, Chapter 1 – The Scope of Power Quality.
1.1 Definition of Power Quality
The Institute of Electrical and Electronic Engineers (IEEE) defines power quality as:
“The concept of powering and grounding electronic equipment in a manner that is suitable to the operation of that equipment and compatible with the premise wiring system and other connected equipment.” 1
Making sure that power and equipment are suitable for each other also means that there must be compatibility between the electrical system and the equipment it powers. Th ere should also be compatibility between devices that share the electrical distribution space. This concept is called Electromagnetic Compatibility (“EMC”) and is defined as:
“the ability of an equipment or system to function satisfactorily in its electromagnetic environment without introducing intolerable electromagnetic disturbances to anything in that environment.” 2
The best measure of power quality is the ability of electrical equipment to operate in a satisfactory manner, given proper care and maintenance and without adversely aff ecting the operation of other electrical equipment connected to the system.
1 – IEEE-Std 1100-1999, IEEE Recommended Practice for Powering and Grounding Electronic Equipment, New York, IEEE 1999. 2 – A definition from the IEC at http://www.iec.ch/zone/emc/whatis.htm
1.2 Voltage
The voltage produced by utility electricity generators has a sinusoidal waveform with a frequency of 60 Hz in North America and 50 Hz in many other parts of the world. This frequency is called the fundamental frequency.
Figure 1: Pure Sinusoidal AC Voltage Waveform
Any variation to the voltage waveform, in magnitude or in frequency, is called a power line deviation. However, not all power line deviations result in disturbances that can cause problems with the operation of electrical equipment.
1.2.1 Voltage Limits
Excessive or reduced voltage can cause wear or damage to an electrical device. In order to provide standardization, recommended voltage variation limits at service entrance points are specified by the electrical distributor or local utility. An example of typical voltage limits is shown in the table below.
Table: Typical Voltage Limits
In addition to system limits, Electrical Codes specify voltage drop constraints; for instance:
(1) The voltage drop in an installation shall:
Be based upon the calculated demand load of the feeder or branch circuit.
Not exceed 5% from the supply side of the consumer’s service (or equivalent) to the point of utilization.
Not exceed 3% in a feeder or branch circuit.
(2) The demand load on a branch circuit shall be the connected load, if known, otherwise 80% of the rating of the overload or over-current devices protecting the branch circuit, whichever is smaller.3
3 – Check with your local Authority Having Jurisdiction for rules in your area.
For voltages between 1000 V and 50 000 V, the maximum allowable variation is typically ±6% at the service entrance. There are no comparable limits for the utilization point. These voltage ranges exclude fault and temporary heavy load conditions. An example of a temporary heavy load condition is the startup of a motor. Since motors draw more current when they start than when they are running at their operating speed, a voltage sag may be produced during the initial startup.
Figure 2: RMS Voltage and Current Produced when Starting a Motor
(Reproduced with Permission of Basic Measuring Instruments, from “Handbook of Power Signatures”, A. McEachern, 1988)
It is not technically feasible for a utility to deliver power that is free of disturbances at all times. If a disturbance-free voltage waveform is required for the proper operation of an electrical product, mitigation techniques should be employed at the point of utilization.
1.3 Why Knowledge of Power Quality is Important
Owning or managing a concentration of electronic, control or life-safety devices requires a familiarity with the importance of electrical power quality.
Power quality difficulties can produce significant problems in situations that include:
Important business applications (banking, inventory control, process control)
Critical industrial processes (programmable process controls, safety systems, monitoring devices)
Essential public services (paramedics, hospitals, police, air traffic control)
Power quality problems in an electrical system can also quite frequently be indicative of safety issues that may need immediate corrective action. Th is is especially true in the case of wiring, grounding and bonding errors.
Your electrical load should be designed to be compatible with your electrical system. Performance measures and operating guidelines for electrical equipment compatibility are available from professional standards, regulatory agency policies and utility procedures.
1.4 Major Factors Contributing to Power Quality Issues
The three major factors contributing to the problems associated with power quality are:
Use of Sensitive Electronic Loads
The electric utility system is designed to provide reliable, efficient, bulk power that is suitable for the very large majority of electrical equipment. However, devices like computers and digital controllers have been widely adopted by electrical end-users. Some of these devices can be susceptible to power line disturbances or interactions with other nearby equipment
The Proximity of Disturbance-Producing Equipment
Higher power loads that produce disturbances – equipment using solid state switching semiconductors, arc furnaces, welders and electric variable speed drives – may cause local power quality problems for sensitive loads.
Source of Supply
Increasing energy costs, price volatility and electricity related reliability issues are expected to continue for the foreseeable future. Businesses, institutions and consumers are becoming more demanding and expect a more reliable and robust electrical supply, particularly with the installation of diverse electrical devices. Compatibility issues may become more complex as new energy sources and programs, which may be sources of power quality problems, become part of the supply solution. These include distributed generation, renewable energy solutions, and demand response programs.
Utilities are regulated and responsible for the delivery of energy to the service entrance, i.e., the utility meter. The supply must be within published and approved tolerances as approved by the regulator. Power quality issues on the “customer side of the meter” are the responsibility of the customer. It is important therefore, to understand the source of power quality problems, and then address viable solutions.
1.5 Supply vs. End Use Issues
Many studies and surveys have attempted to define the percentage of power quality problems that occur as a result of anomalies inside a facility and how many are due to problems that arise on the utility grid. While the numbers do not always agree, the preponderance of data suggests that most power quality issues originate within a facility; however, there can be an interactive effect between facilities on the system.
Does this matter? After all, 100% of the issues that can cause power quality problems in your facility will cause problems no matter where they originate. If the majority of power quality issues can be controlled in your own facility, then most issues can be addressed at lower cost and with greater certainty. Understanding how your key operational processes can be protected will lead to cost savings.
Utilities base their operational quality on the number of minutes of uninterrupted service that are delivered to a customer. Th e requirements are specific, public and approved by the regulator as part of their rate application (often referred to as the ‘Distributors Handbook’).
While some issues affecting the reliability of the utility grid – such as lightning or animal caused outages – do lead to power quality problems at a customer’s facilities, the utility cannot control these problems with 100% certainty. Utilities can provide guidance to end users with power quality problems but ultimately these key principles apply:
Most PQ issues are end-user issues
Most supply issues are related to utility reliability
1.6 Countering the Top 5 PQ Myths
1) Old Guidelines are NOT the Best Guidelines
Guidelines like the Computer Business Equipment Manufacturers Association Curve (CBEMA, now called the ITIC Curve) and the Federal Information Processing Standards Pub94 (FIPS Pub94) are still frequently cited as being modern power quality guidelines.
The ITIC curve is a generic guideline for characterizing how electronic loads typically respond to power disturbances, while FIPS Pub 94 was a standard for powering large main-frame computers.
Contrary to popular belief, the ITIC curve is not used by equipment or power supply designers, and was actually never intended for design purposes. As for the FIPS Pub 94, it was last released in 1983, was never revised, and ultimately was withdrawn as a U.S. government standards publication in November 1997. While some of the information in FIPS Pub 94 is still relevant, most of it is not and should therefore not be referenced without expert assistance.
2) Power Factor Correction DOES NOT Solve All Power Quality Problems
Power factor correction reduces utility demand charges for apparent power (measured as kVA, when it is metered) and lowers magnetizing current to the service entrance. It is not directly related to the solution of power quality problems. There are however many cases where improperly maintained capacitor banks, old PF correction schemes or poorly designed units have caused significant power quality interactions in buildings.
The best advice for power factor correction is the same as the advice for solving power quality issues; properly understand your problem first. A common solution to power factor problems is to install capacitors; however, the optimum solution can only be found when the root causes for the power factor problems are properly diagnosed. Simply installing capacitors can often magnify problems or introduce new power quality problems to a facility.
Power factor correction is an important part of reducing electrical costs and assisting the utility in providing a more efficient electrical system. If power factor correction is not well designed and maintained, other power quality problems may occur. The electrical system of any facility is not static. Proper monitoring and compatible design will lead to peak efficiency and good power quality.
3) Small Neutral to Ground Voltages DO NOT Indicate a Power Quality Problem
Some people confuse the term “common mode noise” with the measurement of a voltage between the neutral and ground wires of their power plug. A small voltage between neutral to ground on a working circuit indicates normal impedance in the wire carrying the neutral current back to the source. In most situations, passive “line isolation” devices and “line conditioners” are not necessary to deal with Neutral to Ground voltages.
4) Low Earth Resistance is NOT MANDATORY for Electronic Devices
Many control and measurement device manufacturers recommend independent or isolated grounding rods or systems in order to provide a “low reference earth resistance”. Such recommendations are often contrary to Electrical Codes and do not make operational sense. Bear in mind that a solid connection to earth is not needed for advanced avionics or nautical electronics!
5) Uninterruptible Power Supplies (UPS) DO NOT Provide Complete Power Quality Protection
Not all UPS technologies are the same and not all UPS technologies provide the same level of power quality protection. In fact, many lower priced UPS systems do not provide any power quality improvement or conditioning at all; they are merely back-up power devices. If you require power quality protection like voltage regulation or surge protection from your UPS, then make sure that the technology is built in to the device.
1.7 Financial and Life Cycle Costs
The financial and life cycle costs of power quality issues are two fold;
The “hidden cost” of poor power quality. The financial impact of power quality problems is often underestimated or poorly understood because the issues are often reported as maintenance issues or equipment failures. Th e true economic impact is often not evaluated.
The mitigation cost or cost of corrective action to fix the power quality issue. The costs associated with solving or reducing power quality problems can vary from the inexpensive (i.e., checking for loose wiring connections), to the expensive, such as purchasing and installing a large uninterruptible power supply (UPS).
Evaluation of both costs should be included in the decision process to properly assess the value, risk and liquidity of the investment equally with other investments. Organizations use basic financial analysis tools to examine the costs and benefits of their investments. Power quality improvement projects should not be an exception; however, energy problems are often evaluated using only one method, the ‘Simple Payback’. The evaluation methods that can properly include the impact of tax and cost of money are not used, e.g., Life Cycle Costing.
Monetary savings resulting from decreased maintenance, increased reliability, improved efficiency, and lower repair bills reduce overall operating costs. A decrease in costs translates to an increase in profit, which increases the value of the organization.
Regrettably, the energy industry has adopted the Simple Payback as the most common financial method used. Simple Payback is admittedly the easiest, but does not consider important issues. To properly assess a capital improvement project, such as a solution to power quality, Life Cycle Costing can be used. Both methods are described below.
1.7.1 Simple Payback
Simple Payback is calculated by dividing the initial, upfront cost of the project (the ‘first cost’), by the annual savings realized. The result is the number of years it takes for the savings to payback the initial capital cost. For example, if the first cost of a power quality improvement project was $100,000, and the improvements saved $25,000 annually, the project would have a four year payback.
As the name implies, the advantage of the Simple Payback method is that it is simple to use. It is also used as an indicator of both liquidity and risk. Th e cash spent for a project reduces the amount of money available to the rest of the organization (a decrease in liquidity), but that cash is returned in the form of reduced costs and higher net profit (an increase in liquidity). Thus the speed at which the cash can be ‘replaced’ is important in evaluating the investment.
Short payback also implies a project of lesser risk. As a general rule, events in the short-term are more predictable than events in the distant future. When evaluating an investment, cash flow in the distant future carries a higher risk, so shorter payback periods are preferable and more attractive.
A very simple payback analysis may ignore important secondary benefits that result from the investment. Direct savings that may occur outside the immediate payback period, such as utility incentive programs or tax relief, can often be overlooked.
1.7.2 Life Cycle Costing
Proper financial analysis of a project must address more than just ‘first cost’ issues. By taking a very short-term perspective, the Simple Payback method undervalues the total financial benefit to the organization. Cost savings are ongoing, and continue to positively impact the bottom line of the company long after the project has been ‘repaid’.
A full Life Cycle Costing financial analysis is both more realistic, and more powerful. Life Cycle Costing looks at the financial benefits of a project over its entire lifetime. Electrical equipment may not need replacing for 10 years or more, so Life Cycle Costing would consider such things as the longer life of the equipment, maintenance cost savings, and the potential increased cost of replacement parts. In these cases, the time value of money is an important part of the investment analysis. Simply stated, money received in the future is less ‘valuable’ than money received today. When evaluating long-term projects, cash gained in the future must therefore be discounted to reflect its lower value than cash that could be gained today.
1.7.3 The Cost of Power Quality Problem Prevention
The costs associated with power quality prevention need to be included with the acquisition cost of sensitive equipment so that the equipment can be protected from disturbances. Installation costs must also be factored into the purchase of a major electrical product. Th e design and commissioning of data centres is a specific example. The costs that should be considered include:
Site preparation (space requirements, air conditioning, etc.)
Installation
Maintenance
Operating costs, considering efficiency for actual operating conditions
Parts replacement
Availability of service on equipment
Consulting advice (if applicable)
Mitigating equipment requirements
The cost of purchasing any mitigating equipment must be weighed with the degree of protection required. In a noncritical application, for instance, it would not be necessary to install a UPS system to protect against power interruptions.
Power supply agreements with customers specify the responsibilities of both the supplier and the customers with regard to costs.
For very large electrical devices, even if no power quality problems are experienced within the facility, steps should be taken to minimize the propagation of disturbances which may originate and reflect back into the utility distribution system. Many jurisdictions regulate the compatibility of electrical loads in order to limit power quality interactions.
Published by Electrotek Concepts, Inc., PQSoft Case Study: Voltage Notching and Distribution Systems – Large Induction Motor Drive, Document ID: PQS0320, Date: July 18, 2003.
Abstract: This case describes voltage notching associated with large adjustable speed drives. The notching is a normal characteristic of a phase-controlled rectifier but this paper illustrates problems that can occur on systems with low short circuit levels where the voltage notching can excite the natural frequency of the distribution system and cause significant distortion in the supply voltage. The notching characteristics and the interaction with the distribution system frequency response characteristics are described, along with possible solutions, An example problem and the corresponding solution associated with a large 6000 hp ASD is presented.
INTRODUCTION
Adjustable speed ac and dc drives are used with very large motors (e.g. 1,000-20,000 hp) for a variety of reasons. The drives can result in significantly improved efficiency when the driven load is variable. For large motor applications on weak systems, the drives may be required for motor starting to avoid high inrush currents.
Adjustable speed ac drives (ASDs) 1000 hp and larger typically use phase-controlled rectifiers (SCRs) and a large dc link inductor to supply a relatively constant dc current to the inverter. This is known as a current source inverter (CSI) configuration. The input rectifier may be configured as a six pulse, twelve pulse, or even higher pulse number rectifier, depending on harmonic control requirements. For dc drive applications, phase-controlled rectifiers are used to supply the dc current directly to the dc motor.
The voltage notching discussed in this paper is caused by the commutating action of the controlled rectifier. Whenever the current is commutated from one phase to another, there is a momentary phase-to-phase short circuit through the rectifier switching devices (SCRs, in this case). For a six pulse converter, this happens six times each cycle. The voltage notch is defined by its duration and its depth. The duration (commutation period) is determined by the source inductance to the drive and the current magnitude. The depth of the notch is reduced by inductance between the observation point and the drive (e.g. isolation transformer or choke inductance). An example waveform illustrating simple notches resulting from a drive operation is shown in Figure 1.
Figure 1 – Voltage Notches caused by Converter Commutation
PROBLEM DESCRIPTION
On most systems, problems with voltage notching can be minimized by applying sufficient isolation reactance at the drive. This limits the notch magnitude on the source side of the isolation reactance. However, on some systems, the notches that appear at the system level can still be significant. If there is not much resistive load on a system like this, the notches can excite the natural frequency of the distribution system (determined by the capacitance of lines, cables, and capacitor banks in parallel with the system source inductance) and cause significant distortion in the voltage waveform.
Numerous papers have described the voltage notching phenomena in industrial facilities and sizing isolation reactance to limit the notching effect on other loads [1-5]. However, there has been little literature describing the potential for voltage notching to excite natural frequencies of the distribution system. The high frequency oscillations that result can cause problems with communication interference and sensitive customer loads. This paper describes the concern and possible solutions using an example where a problem was encountered. The methodology for evaluating these problems and the solutions implemented should be valuable to anyone else encountering this problem.
It is important to note that the notching problem described should only exist with large adjustable speed drives with current-source inverter configurations or with dc drives. With other types of ASDs that use voltage source inverters (e.g. pulse width modulation), the rectifier does not have a constant dc current that needs to be commutated from one switching device to another. It is this current being commutated that that essentially looks like an injection of a disturbing current into the distribution system.
LARGE INDUCTION MOTOR DRIVE
The example system is illustrated by the one line diagram in Figure 2. The 25kV distribution system is supplied through a 10 MVA transformer from the 144kV transmission system. The customer causing the notching problems has a 6000 hp induction motor supplied through an adjustable speed drive. This drive is at a 4.16kV bus supplied through a 7.5 MVA transformer. Harmonic filters (5th, 7th, and 11th) are included to control the lower order characteristic harmonics of the six pulse drive.
Another customer on a parallel feeder supplied from the same 25kV bus has motor loads at both 4.16kV (800 hp motor) and 480 volts. The 800 hp motor includes surge capacitors for transient protection. The customer also has power factor correction capacitors at the 480 volt bus. These lower voltage surge capacitors and power factor correction capacitors have the potential to magnify the oscillations which occur on the distribution system.
Operation of the 6000 hp motor and drive resulted in significant oscillations on the 25kV supply system. These oscillations caused clocks to run fast at the customer with the 6000 hp motor (clocks were fed separately from the 25kV system) and failure of surge capacitors on the 800 hp motor at the customer located on the parallel feeder.
Figure 2 – Oneline Diagram for the System
Figure 3 illustrates the measured waveforms on the 25kV supply system. The oscillations have a primary frequency component near the 60th harmonic. In this case, the natural frequency is the result of the line capacitance from approximately 12 km of overhead line in parallel with the system source inductance. Note that the oscillations are excited six times per cycle corresponding to the six-pulse operation of the drive.
System Frequency Response
A model was developed using the Electromagnetic Transients Program (EMTP) to evaluate the magnification at the surge capacitor location and to evaluate possible solutions to the problem. First of all, the steady state frequency response of the system was simulated to illustrate the natural frequency that can excite the oscillations illustrated above. Figure 4 shows the voltage on the 25kV system as a function of a 1 amp source at the 4.16kV bus where the drive is located. The system resonance just above the 60th harmonic is apparent in the figure. Note also the lower order series and parallel resonances caused by the harmonic filters.
Figure 3 – Voltage Waveform and Spectrum on 25kV System
Figure 4 – Voltage vs. Frequency at 25kV Bus
Effect of Customer Low Voltage Capacitors
Next, the actual adjustable speed drive and motor load were represented to reproduce the notching oscillations observed in the measurements. The worst notching problems are associated with a firing angle at about 70% load. The simulated waveform for the 25kV bus voltage is shown in Figure 5 below. The oscillations at each commutation point are in good agreement with the measurement results.
Figure 5 – Simulated 25kV Voltage with Drive Operating
The model was then used to evaluate the voltage waveforms at the customer bus located on the parallel feeder. Figure 6 illustrates the voltage waveform at the 4.16kV bus where the 800 hp motor surge capacitors cause magnification of the oscillations. The potential for problems at this location is quite evident. The surge capacitor failures typically occurred during startup of the drive when the firing angles went through this worst case condition. Figure 7 shows the waveform at the 480 volt bus where the power factor correction capacitors damp out the high frequency oscillation. The power factor correction capacitors are much larger than the surge capacitors and result in a much lower resonant frequency. No problems were encountered with loads on the 480 volt bus.
Figure 6 – Simulated Voltage at Surge Capacitor
Figure 7 – Simulated Voltage at Power Factor Correction Capacitors
Possible Solutions
A number of possible solutions to the high frequency oscillation problem were evaluated. These included:
A larger choke inductance at the input to the adjustable speed drive. This approach could be effective if the choke impedance was included as part of the drive’s initial design. As a retrofit, it is impractical because the size required would cause voltage regulation problems at the drive.
Larger surge capacitors at the 800 hp motor of the parallel customer. This approach is feasible to protect the individual motor and surge capacitors of concern. However, large surge capacitors would be required and they do not eliminate the oscillations on the 25kV system that are the source of the problem. Note that the surge capacitors were removed as a temporary solution for the parallel customer.
Modification of the filtering at the adjustable speed drive to include a high pass filter instead of just tuned branches at the 5th, 7th, and 11th. This approach proved to be ineffective because the high pass filter cannot provide sufficient damping at the higher frequency resonance.
Addition of a capacitor bank on the 25kV system. This approach has the advantage of being the least expensive and the most practical to implement. Simulations show that this solution can be effective.
Effect of a 25kV Capacitor Bank
Adding a capacitor bank to the 25kV system changes the system frequency response to prevent the high frequency oscillation shown on the previous waveforms. However, the capacitor bank creates a new system parallel resonance at a lower frequency that could result in magnification of the lower order harmonic components created by the adjustable speed drive.
The first capacitor bank size tried was 1200 kVAr. This created a resonance that magnified the thirteenth harmonic component on the system if the power factor correction capacitors at the parallel customer were out of service. Figure 8 gives the measured voltage on the 25kV system for this condition. Note that the notching oscillation problem is solved (no high frequency components) but the thirteenth harmonic component in the voltage is approaching 5%.
Figure 8 – Voltage on 25kV System with 1200 kVAr Capacitor bank
After examination of the system frequency response with the drive filters and the existing load power factor correction capacitors, the capacitor size was increased to 2400 kVAr to solve the thirteenth harmonic resonance problem. Figure 9 illustrates the frequency response at the 25kV bus for a 1 amp source located at the 4.16kV drive location.
Figure 9 – Frequency Response on 25kV System with 2400 kVAr Capacitor Bank
With a 2400 kVAr capacitor bank, all of the system resonances that could cause magnification are located below the eleventh harmonic and are at frequencies that are not characteristic harmonics of the drive. Figure 10 gives the measured voltage waveform and harmonic spectrum with the 2400 kVAr capacitor operational. The voltage distortion is less than 2% with the 2400 kVAr capacitor in service.
Figure 10 – Voltage on 25kV System with 2400 kVAr Capacitor Bank
SUMMARY
The case study illustrates the characteristics of high frequency oscillations that can result from the commutation notches of large adjustable speed ac or dc drives operating on systems with relatively low short circuit levels.
The system oscillations can be magnified at customer locations where low voltage capacitors exist. Small capacitors, such as motor surge capacitors can be a particular problem. Even capacitors in the power supplies for electronic loads or smaller adjustable speed drive rectifiers can be affected by these oscillations.
The problem can be solved by careful selection of a capacitor size for the primary distribution system. The capacitor should not introduce a new resonance at one of the characteristic harmonics of the adjustable speed drive. The interaction of the proposed capacitor with other system capacitors and harmonic filters must be evaluated.
REFERENCES
1.J.C. Read, “The Calculation of Rectifier and Converter Performance Characteristics,” Journal of the IEE, vol. 92, pt. II, 1945, pp 495-509.
2.E.F. Christensen, et. al., “Analysis of Rectifier Circuits,” AIEE Transactions, vol. 63, 1944, pp. 1048-1058.
3.R.A. Adams, et. al., “Power Quality Issues Within Modern Industrial Facilities, “IAS Textile Film and Fiber Meeting, Atlanta, GA., 1990.
4.D.A. Jarc and R.G. Schieman, “Powerline Considerations for Variable Frequency Drives, “ IEEE Transactions on IAS, vol. 1A-21, no. 5, 1985.
RELATED STANDARDS IEEE Standard 519
GLOSSARY AND ACRONYMS ASD: Adjustable Speed Drive CSI: Current Source Inverter
Published by Pacific Gas and Electric Company (PG&E)
IEEE Standard 141-1993, Recommended Practice for Electric Power Distribution for Industrial Plants, aka the Red Book. A thorough analysis of basic electrical-system considerations is presented. Guidance is provided in design, construction, and continuity of an overall system to achieve safety of life and preservation of property; reliability; simplicity of operation; voltage regulation in the utilization of equipment within the tolerance limits under all load conditions; care and maintenance; and flexibility to permit development and expansion.
IEEE Standard 142-1991, Recommended Practice for Grounding of Industrial and Commercial Power Systems, aka the Green Book. Presents a thorough investigation of the problems of grounding and the methods for solving these problems. There is a separate chapter for grounding sensitive equipment.
IEEE Standard 242-1986, Recommended Practice for Protection and Coordination of Industrial and Commercial Power Systems, aka the Buff Book. Deals with the proper selection, application, and coordination of the components which constitute system protection for industrial plants and commercial buildings.
IEEE Standard 446-1987, Recommended Practice for Emergency and Standby Power Systems for Industrial and Commercial Applications, aka the Orange Book. Recommended engineering practices for the selection and application of emergency and standby power systems. It provides facility designers, operators and owners with guidelines for assuring uninterrupted power, virtually free of frequency excursions and voltage dips, surges, and transients.
IEEE Standard 493-1997, Recommended Practice for Design of Reliable Industrial and Commercial Power Systems, aka the Gold Book. The fundamentals of reliability analysis as it applies to the planning and design of industrial and commercial electric power distribution systems are presented. Included are basic concepts of reliability analysis by probability methods, fundamentals of power system reliability evaluation, economic evaluation of reliability, cost of power outage data, equipment reliability data, examples of reliability analysis. Emergency and standby power, electrical preventive maintenance, and evaluating and improving reliability of the existing plant are also addressed.
IEEE Standard 519-1992, Recommended Practices and Requirements for Harmonic Control in Electrical Power Systems. This guide applies to all types of static power converters used in industrial and commercial power systems. The problems involved in the harmonic control and reactive compensation of such converters are addressed, and an application guide is provided. Limits of disturbances to the AC power distribution system that affect other equipment and communications are recommended. This guide is not intended to cover the effect of radio frequency interference.
IEEE Standard 929-1988, Recommended Practice for Utility Interface of Residential and Intermediate Photovoltaic (PV) Systems.
IEEE Standard 1100-1999, Recommended Practice for Powering and Grounding Sensitive Electronic Equipment, aka the Emerald Book. This is the first revision of the original edition in 1992. Recommended design, installation, and maintenance practices for electrical power and grounding (including both power-related and signal-related noise control) of sensitive electronic processing equipment used in commercial and industrial applications.
IEEE Standard 1159-1995, Recommended Practice for Monitoring Electric Power Quality. Monitoring of electric power quality of AC power systems, definitions of power quality terminology, impact of poor power quality on utility and customer equipment, and the measurement of electromagnetic phenomena are covered. Key chapters include: Monitoring objectives, Measurement instruments, monitor application techniques, and interpreting monitoring results.
IEEE Standard 1250-1995, Guide for Service to Equipment Sensitive to Momentary Voltage Disturbances. Computers, computer-like products, and equipment using solid- state power conversion have created entirely new areas of power quality considerations. There is an increasing awareness that much of this new user equipment is not designed to withstand the surges, faults, and reclosing duty present on typical distribution systems.
Momentary voltage disturbances occurring in ac power distribution and utilization systems, their potential effects on this new, sensitive, user equipment, and guidance toward mitigation of these effects are described. Harmonic distortion limits are also discussed.
IEEE Standard 1346-1998, Recommended Practice for Evaluating Electric Power System Compatibility with Electronic Process Equipment. A standard methodology for the technical and financial analysis of voltage sag compatibility between process equipment and electric power systems is recommended. The methodology presented is intended to be used as a planning tool to quantify the voltage sag environment and process sensitivity. It shows how technical and financial alternatives can be evaluated. Performance limits for utility systems, power distribution systems, or electronic process equipment are not included.
All the above IEEE standards are available from The Institute of Electrical and Electronics Engineers, Inc.
SEMI F-47-1999, Standard for Definition and Measurement of Equipment Reliability, Availability, and Maintainability defines the sag ride through capability.
SEMI F-42-1999, Test Method for Semiconductor Processing Equipment Voltage Sag Immunity defines the test methodology to confirm compliance to the standard.
SEMI standards are available from Semiconductor Equipment and Materials International (SEMI), 805 East Middlefied Road, Mountain View, CA 94043. The web address is http://www.semi.org/.
UL 1449 second edition, 1998. Underwriters Laboratories, Inc. standard 1449 is a safety, construction, and performance standard for transient voltage surge suppressors. The second edition revision includes withstand for loss of neutral condition without damage to the suppressor. UL local address is 1655 Scott Boulevard, Santa Clara, CA 95050-4169. Telephone: (408) 985-2400.
NFPA 70-1999, National Electrical Code. Published by the National Fire Protection Association, Batterymarch Park, Quincy, MA 02269. Available in most book stores. The NEC is basically a safety code to protect electrical distribution circuits from faults and overloads. It is not a performance code.
ANSI C84.1-1995, Electric Power Systems and Equipment – Voltage Ratings. Published by NEMA, National Electrical Manufacturers Association, 1300 North 17th Street, Suite 1847, Rosslyn, Virginia 22209. Telephone: (703) 841-3200. This voluntary standard was first approved in 1954 as a joint effort by the Edison Electric Institute and the NEMA to recommend voltage ratings for both electric systems and equipment to promote compatibility. ANSI stands for American National Standards Institute. This ANSI standard establishes the steady state voltage delivery window of +/- 5% at the point of delivery. It also recommends a tolerance window of +6% and -13% for end use equipment. The standard also establishes a tolerance window for voltage unbalance of +/-3%.
NEMA MG 1- 1998, Motors and Generators. National Electrical Manufacturers Association, 2101 L Street, N.W. Washington DC 20037. This standard gives technical specifications used by manufacturers. Power quality concerns that can be referenced include: voltage and current unbalance tolerance, over and under voltage tolerance, electrical starting characteristics, and insulation values.
NEMA Standards Publication No. LS1-1992, Low Voltage Surge Protective Devices. This is a good standard for quality construction of the device.
Published by J. R. Maglin & R. Ramesh, Department of Electrical and Electronics Engineering, Anna University, Chennai-25, India, E-mail: rramesh@annauniv.edu, Tel: +91-9444217600 Published in European Journal of Scientific Research ISSN 1450-216X Vol.61 No.2 (2011), pp. 321-327 http://www.eurojournals.com/ejsr.htm
Abstract
The main objective of this paper is to identify the problems associated with solar converters in the solar power system due to the involvement in more number of power electronics components. The main objective of this work is to study of the behaviors of the solar PV systems and the power quality issues in converters. Harmonics are created by the switching system of the power electronic circuit and can cause damage to power equipment on the utility side and sensitive loads on the customer side.
Keywords: Converters, Inverters, PV, Power quality
1. Introduction
Government promotion of renewable energy sources has led to several large scale solar power plants in India. India receives solar energy in the region of 5 to 7 kWh/m2 for 300 to 330 days in a year. This energy is sufficient to set up 20 MW solar power plant per square kilometer land area. With about 300 clear, sunny days in a year, India’s theoretical solar power reception, on only its land area, is about 5 Petawatt-hours per year (PWh/yr) (i.e. 5 trillion kWh/yr or about 600 TW). The daily average solar energy incident over India varies from 4 to 7 kWh/m2 with about 1500–2000 sunshine hours per year (depending upon location), which is far more than current total energy consumption. For example, assuming the efficiency of PV modules were as low as 10%, this would still be a thousand times greater than the domestic electricity demand(in India) projected for 2015. The amount of solar energy produced in India is less than 1% of the total energy demand. The grid interactive solar power as of December 2010 was merely 10 MW. Government-funded solar energy in India only accounted for approximately 6.4 MW-yr of power as of 2005. However, as of October 2009, India is currently ranked number one along with the United States in terms of installed solar power generation capacity.
In those installations, a large amount of relatively low power inverters is connected to a common AC low voltage bus and high voltage distortion levels have been reported although the single inverters comply to the harmonic emission standard.
2. Role of Power Electronic Components in Solar Power System
Grid-connected PV systems are currently being widely installed in many of the developed countries [1]. In addition to their environmental benefits, PV systems have a number of technical and economical benefits. They can be operated to decrease the losses and improve the voltage profile of the feeder to which they are connected [2], [3]. One of the main characteristics of PV systems is the high variability of their output power. The variability stems from the fact that these systems are static, and thus, any instantaneous change in the irradiance reaching the PV arrays leads to a corresponding change in their output power. The time frame for the short-term fluctuations in irradiance is in the order of seconds to few minutes [4], [5]; thus, some studies have considered the fluctuations in the PV power to be within the same time frame [6], [7]. However, other studies have recommended the use of 10-min irradiance data when studying the power fluctuations generated from PV systems [8], [9].
This is especially suitable for systems with ratings in the order of tens of megawatts that extend over a large land area, such as the 10-MW PV plant in Pocking, Germany [10]. A recent report published by the North American Electric Reliability Corporation showed that the output power of existing large PV systems, with ratings in the order of tens of megawatts, can change by 70% in a five to ten-min time frame [11]. It should be noted that for a number of small systems that are distributed over a large land area, the resulting combined fluctuations are much less due to the smoothing effect [12], [13]. Also, the fluctuation in the power of these systems can lead to unstable operation of the electric network prior to the fault conditions, high power swings in the feeders [14]. However, PV power fluctuates depending on weather conditions, season, and geographic location and may cause problems like voltage fluctuation and large frequency deviation in electric power system operation [15],[16],[17]. To date, it has not been necessary for small PV generators to provide frequency regulation services to the power system. In the future, with an increasing penetration of PV generation, their impact upon the overall control of the power system will become significant [18]. This will lead a situation where the PV generators will be required to share some of the duties, such as load frequency control.
The increasing number of renewable energy sources and distributed generators requires new strategies for the operation and management of the electricity grid in order to maintain or even to improve the power-supply reliability and quality. The power-electronic technology plays an important role in distributed generation and in integration of renewable energy sources into the electrical grid, and it is widely used and rapidly expanding as these applications become more integrated with the grid-based systems. During the last few years, power electronics has undergone a fast evolution, which is mainly due to two factors. The first one is the development of fast semiconductor switches that are capable of switching quickly and handling high powers. The second factor is the introduction of real-time computer controllers that can implement advanced and complex control algorithms. These factors together have led to the development of cost-effective and grid-friendly converters. Regardless of the power ratings of the alternative energy generation unit, it has to be converted to a suitable form by utilizing power electronic converters. In this paper[19], new trends in power-electronic technology for the integration of renewable energy sources and energy-storage systems are presented. Therefore, power electronics is vital to the future energy systems and process of green industrialization.
3. Power Quality Issues in Converters
Typical power electronic converters arrangements for PV systems are shown [20].Authors [21] discussed the many sources of nonlinearity in power electronics systems. Authors demonstrated with an analytical and experimental result and proved that complex nonlinear phenomena such as sub harmonics, quasi periodicity and chaos can arise in even the simplest power electronic systems. Switched mode dc-dc converters inherently produce ripple at the switching frequency and its harmonics. The unwanted signal which appears at both the input and the output is undesirable for electromagnetic compatibility. Filtering must generally be employed to reduce it to an acceptable level [22].Switched-mode DC-DC converters are nonlinear and time-varying systems. In unsteady nonlinear systems a variety of strange effects are observed, including sub harmonics, quasi periodic oscillation, intermittency, and chaotic behavior, apparently random motion. Because closed loop buck converters are strongly nonlinear system, plenty of nonlinear phenomena may occur at operation, which will result in the instability of the system [23]. Lupco V. Karadzino and David C. Hamill [21] highlighted that all switching converters have some stray inductance in series with their diodes, so we expect the phenomena to be widespread, especially as switching frequencies are pushed ever higher. The various power qualities such as voltage and frequency profiles, THD in voltages and currents and voltage and current unbalance factors have been measured for renewable energy using a power quality analyzer [25].
4. Power Quality Issues in Inverters
With the increase of the renewable energy penetration to the grid, power quality (PQ) of the medium to the low voltage power transmission system is becoming a major area of interest. Most of the integration of renewable energy system to the grid takes place with the aid of power electronics converters. The main purpose of the power electronic converters is to integrate the distributed generation (DG) to the grid in compliance with power quality standards. However, high frequency switching of inverters can inject additional harmonics to the system, creating major PQ problems if not implemented properly [26]. Bosman[27] experimentally showed that a distorted grid voltage can significantly influence the harmonic content of the current injected by the inverter. In this paper, Photovoltaic connected to grid is used as power supply to the load [28]. A laboratory setup was established to perform the measurement. Approximately 70-80% of all power quality related problems can be attributed to faulty connections and/or wiring [29]. Power frequency disturbances, electromagnetic interference, transients, harmonics and low power factor are the other categories of PQ problems that are related to source of supply and types load [30].
Though the output of a PV panel depends on the solar intensity and cloud covers, the PQ problems not only depends on irradiance but also are based on the overall performance of solar photovoltaic system including PV modules, inverter, filters controlling mechanism etc. Studies presented in [31], show that the short fluctuation of irradiance and cloud cover play an important role for low voltage distribution grids with high penetration of PV. Therefore special attention should be paid to the voltage profile and the power flow on the line. It also suggests that voltage and power mitigation can be achieved in super capacitors which result in an increase of about 20% in the cost of the PV system. Voltage swell may also occur when heavy load is removed from the connection. Concerning DG, voltage disturbance can cause the disconnection of inverters from the grid and therefore result in loss of energy. Also long term performance of grid connected PV system shows a remarkable degradation of efficiency due to the variation of source and performance of inverter [32]. The PV array can be single or a string of PV panels either in series or parallel mode connection. Centralized or decentralized mode of PV systems can also be used and the overview of these PV Inverter-Grid connection topologies along with their advantages and disadvantages are discussed in [33]. These power electronic converters, together with the operation of non-linear appliances, inject harmonics to the grid. In addition to the voltage fluctuation due to irradiation, cloud cover or shading effects could make PV system unstable in terms of grid connection. Therefore this needs to be considered in the controller design for the inverter [34], [35]. In general grid connected PV inverter is not able to control the reactive and harmonic currents drawn from non-linear loads. An interesting controlling mechanism has been presented in [36] where a PV system is used as an active filter to compensate the reactive and harmonic as well as injecting power to the grid. This system can also operate in standalone mode.
5. Power Quality Issues in Grid Connected Solar Power System
The general solar power system is shown in figure.1. The major components include boost converters and inverters.
Figure 1: Basic Block Diagram
Converter − A boost converter is a DC-DC converter with an output voltage greater than the source voltage. The aim is to analyze and design the high efficient modified converters to extract maximum power from solar PV panels.
Inverter − Multilevel inverters offer high power capability, associated with lower output harmonics and lower commutation losses. The new topology has a significant reduction in the number of power devices and capacitors required to implement a multilevel output. Additionally, the dedicated modulator circuit required for multilevel inverter operation will be implemented using a control circuit, reducing overall system cost and complexity.
Controller − The embedded controller will fetch the input from the sensor and give command to the motor to run in order to tackle the change in the position of the sun. And also controller monitors the various electrical parameters and generates the control signal to solve the power quality issues.
Power quality is certainly a major concern in the present era; it becomes especially important with the introduction of sophisticated devices, whose performance is very sensitive to the quality of power supply. Modern industrial processes are based a large amount of electronic devices such as programmable logic controllers and adjustable speed drives. The electronic devices are very sensitive to disturbances and thus industrial loads become less tolerant to power quality problems such as voltage dips, voltage swells, and harmonics. The distortion in the quality of supply power can be introduced /enhanced at various stages; however, some of the primary sources of distortion [24] can be identified as Power Electronic Devices, IT and Office Equipments, Arcing Devices, Load Switching, Large Motor Starting, Embedded Generation Electromagnetic Radiations and Cables Storm and Environment Related Causes etc. Authors presented [38] a survey of the techniques for reduction of harmonics. Fundamental ways are given to reduce harmonics by means of active and passive methods. Especially active ways are focused on, because they can be integrated into power electronic converters. Beside their prime task of converting power, these converters have thus the potential to deliver an ancillary service, namely: active harmonic reduction. Authors proposed [39] a hybrid active filter for the damping of harmonic resonance in industrial power systems. The hybrid filter consists of a small rated active filter and a 5th-tuned passive filter. The active filter is characterized by detecting the 5th harmonic current flowing into the passive filter. Experimental results obtained from a 20-kW laboratory model verify the viability and effectiveness of the hybrid active filter proposed. Walid and Kazerani [54] investigated the methods that can be used to reduce the fluctuations in the power generated from large PV systems. The authors suggested to use the of battery storage systems , use of dump load and curtailment of the generated power by operating the power-conditioning unit of the PV system below the maximum power point to reduce the fluctuations in large PV system. And also authors examined the economic aspects of using different methods for smoothing the output power of large PV systems. Authors [47] presented a grid-connected photovoltaic (PV) system with direct coupled power quality controller (PQC). The proposed PV system used an inner current control loop and outer feedback control loops to improve grid power quality and maximum power point tracking (MPPT) of PV arrays.
6. Conclusion
This paper has provided a brief summary of solar PV systems and power quality issues in grid connected power system. This paper has also presents a summary of converts and inverters in solar power system and its power quality issues. Suitable control techniques are also discussed briefly. The intention of the authors was simply to provide groundwork to readers interested in looking back on the evolution of power quality issues in PV systems, and to consider where to go from here.
References
[1] Trends in photovoltaic applications: Survey report of selected IEA countries between 1992 and (2008). [Online]. Available: http://www.iea-pvps.org/. [2] B. H. Chowdhury and A. W. Sawab, “Evaluating the value of distributed photovo1aic generations in radial distribution systems,” IEEE Trans.Energy Convers., vol. 11, no. 3, pp. 595–600, Sep. 1996. [3] N. Srisaen and A. Sangswang, “Effects of PV grid-connected system location on a distribution system,” in Proc. IEEE Asia Pac. Conf. Circuits Syst. 2006, 4–7 Dec., pp. 852–855. [4] W. Jewell and T. Unruh, “Limits on cloud-induced fluctuation in photovoltaic generation,” IEEE Trans. Energy Convers., vol. 5, no. 1, pp. 8–14, Mar. 1990. [5] A. Woyte, R. Belmans, and J. Nijs, “Fluctuations in instantaneous clearness index: Analysis and statistics,” Solar Energy, vol. 81, no. 2, pp. 195–206, Feb. 2007. [6] W. T. Jewell and R. Ramakumar, “The effects of moving clouds on electric utilities with dispersed PV generation,” IEEE Trans. Energy Convers., vol. EC-2, no. 4, pp. 570–576, Dec. 1987. [7] A. Woyte, V. Van Thong, R. Belmans, and J. Nijs, “Voltage fluctuations on distribution level introduced by photovoltaic systems,” IEEE Trans.Energy Convers., vol. 21, no. 1, pp. 202–209, Mar. 2006. [8] G. Vijayakumar, M. Kummert, S. Klein, and W. Beckman, “Analysis of short-term solar radiation data,” Solar Energy, vol. 79, pp. 495–504, 2005. [9] C. Craggs, E.M. Conway, and N. M. Pearsall, “Statistical investigation of the optimal averaging time for solar irradiance on horizontal and vertical surfaces in the U.K,” Solar Energy, vol. 68, pp. 179–187, 2000. [10] Solar Server, “The world’s largest photovoltaic solar power plant is in Pocking,” [Online]. Available: http://www.solarserver.com/solarmagazin/anlage_0606_e.html. [11] North American Electric Reliability Corp. (Apr. 2009). Accommodating High Levels of Variable Generation [Online]. Available:http://www.nerc.com/files/IVGTF_Report_041609.pdf [12] E. Wiemken, H. G. Beyer, W. Heydenreich, and K. Kiefer, “Power characteristics of PV ensembles: Experiences from the combined power production of 100 grid connected pv systems distributed over the area of germany,” Solar Energy, vol. 70, no. 6, pp. 513–518, 2001. [13] K. Otani, J. Minowa, and K. Kurokawa, “Study on areal solar irradiance for analyzing a really totalized PV systems,” Solar Energy Mater. SolarCells, vol. 47, pp. 281–288, 1997. [14] Y. T. Tan and D. S. Kirschen, “Impact on the power system of a large penetration of photovoltaic generation,” in Proc. IEEE Power Eng. Soc.Gen. Meet, Jun. 24–28, 2007, pp. 1–8. [15] S. Yanagawa, T. Kato, K. Wu, A. Tabata, and Y. Suzuoki, “Evaluation of LFC capacity for output fluctuation of photovoltaic generation systems based onmulti-point observation of insolation,” in Proc. IEEE Power Eng. Soc. Summer Meeting, 2001, pp. 1652–1657. [16] A. Woyte, V. V. Thong, R. Belmans, and J. Nijs, “Voltage fluctuations on distribution level introduced by photovoltaic systems,” IEEE Trans.Energy Convers., vol. 21, no. 1, pp. 202–209, Mar. 2006. [17] H. Asano, K. Yajima, and Y. Kaya, “Influence of photovoltaic power generation on required capacity for load frequency control,” IEEE Trans.Energy Convers., vol. 11, no. 1, pp. 188–193, Mar. 1996. [18] Y. T. Tan, D. S. Kirschen, and N. Jenkins, “A model of PV generation suitable for stability analysis,” IEEE Trans. Energy Convers., vol. 19,no. 4, pp. 748–755, Dec. 2004. [19] J. M. Carrasco, L. G. Franquelo, J. T. Bialasiewicz, E. Galvan, R. C. P. Guisado, Ma. A. M. Prats, J. I. Leon, and N. Moreno-Alfonso, “Powerelectronic systems for the grid integration of renewable energy sources: a survey,” IEEE Trans. Ind. Electron., vol. 53, no. 4, pp. 1002 1016, Jun. 2006. [20] M. Elbuluk and N.R.N. Idris The Role Power Electronics in Future Energy Systems and Green Industrialization 2nd IEEE International Conference on Power and Energy (PECon 08), December 1-3, 2008, Johor Baharu, Malaysia. [21] Lupco V. Karadzinov and David C. Hamill “DH Phenomenon in DC/DC Converters”. [22] David C Hamill “ An effiecient active ripple filter for use in dc-dc conversion” IEEE transactions on aerospace and electronic systems vol 32, no, 3 1996 pp.1077-1084. [23] Wang Yuanbin “Research on Chaos in Switching Dc-Dc Converters” 2009 Second International Conference on Intelligent Computation Technology and Automation pp 91-94. [24] John Stones and Alan Collinsion “Introduction to Power Quality” power engineering journal 2001 pages: 58 -64. [25] Manoj Kumar M.V and Rangan Banerjee Power Quality of Renewable Isolated Power Systems – A Case study 5th International Conference on Industrial and Information Systems, ICIIS 2010, Jul 29 – Aug 01, 2010, India. [26] S.K.Khadem, M.Basu and M.F.Conlon, “Power Quality in Grid Connected Renewable Energy Systems: Role of Custom Power Devices”, International Conference on Renewable Energies and Power Quality (ICREPQ’10), Granada (Spain), 23rd-25th March 2010. [27] A.J.A. Bosman, Harmonic modeling of Solar inverters and their interaction with the distribution grid, Master thesis publication of the Eindhoven University of Technology (TUE). Department of Electrical Engineering. Electrical Power Systems, 2006. [28] M. Anwari, , M. Imran Hamid, M. I. M. Rashid, and Taufik, Power Quality Analysis of Grid- Connected Photovoltaic System with Adjustable Speed Drives. [29] S.M.Halpin, L.L.Grigsby, “The Electric Power Engineering Handbook,CRC Press LLC (2001),pp.15.4 [30] C.Sankaran, “Power Quality”, CRC Press (2002), pp.12-13. [31] J.D.Mondol, Y.Yohanis, M.Smyth, B.Norton, “ Long term Performance Analysis of a Gridconnected Photovoltaic System in Northern Ireland”, Energy Conv & Mang,2006,Vol.47,pp.2925-2947. [32] F.Blaabjerg, Z.Chen, S.B.Kjaer, “ Power Electronics as Efficient Interface in Dispersed Power Generation Systems”, IEEE Transactions on Power Electronics 2004, Vol.19 (4), pp.1184- 1194. [33] R.Teodorescu, F.Blaabjerg, M.Liserre, U.Borup, “ A New Control Structure for Grid connected PV Inverters with Zero Steady-State Error and Selective harmonic Compensation,” in Proc.PESC2004, pp.1742-1747. [34] X.Yuan, W.Merk, H.Stemmler, J.Allmeling, “ Stationary Frame Generalized Integrators for Current Control of Active Power Filters with Zero Steady-State Error for Current Harmonics of Concern Under Unbalanced and Distorted Operating Conditions” IEEE Transactions on Industry Applications 2002, Vol.38 (2), pp.523-532. [35] H.Callega, H.Jimenez, “Performance of a Grid-connected PV System used as Active Filter,” Energy Conv & Mang, 2004, Vol.45, pp.2417-2428. [36] G.Chicco, J.Schlabbach, F.Spertino, “Experimental Assessment of the Waveform distortion in Grid-connected Photovoltaic installations”, Solar Energy, 2009, Vol.:83, pp.1026-1039. [37] P.J.M. Heskes J.M.A. Myrzik W.L. Kling (2008) Survey of Harmonic Reduction Techniques Applicable as Ancillary Service of Dispersed Generators Young Researchers Symposium, February 7-8, 2008, Technical University of Eindhoven, The Netherlands. [38] Fujita.H.Yamasaki.T.;Akagi.H.(2000) A hybrid active filter for damping of harmonic resonance in industrial power systems IEEE Transactions on Power Electronics Volume 15, Issue 2, pp:215 – 222. [39] Sung-Hun Ko and Seong-Ryong Lee, Hooman Dehbonei and C.V. Nayar A Grid Connected Photovoltaic System with Direct Coupled Power Quality Control IEEE 2006 pp 5203-5208.
Published by Electrotek Concepts, Inc., PQSoft Case Study: PQ Investigation at a Battery Facility, Document ID: PQS0401, Date: March 30, 2004.
Abstract: An office complex was experiencing continual operational problems with some of their electronic equipment not protected by power conditioning equipment. The equipment would periodically exhibit strange behavior.
An infrared heat detector was used to locate loose wiring connections, and once these connections were fixed, the neutral-to-ground voltages disappeared as well as the equipment problems.
This case presents the results of measurements and analysis of electronic equipment problems.
PROBLEM STATEMENT
An office complex was experiencing continual operational problems with some of their electronic equipment not protected by power conditioning equipment. The equipment would periodically exhibit strange behavior.
What’s Been Done So Far
The facility engineer has contacted the utility and the utility could not correlate any of the equipment problems with any power system faults or other events. He concludes that the problem must be internally generated.
DEVELOP MONITORING PLAN
A thorough monitoring plan was developed to characterize both disturbance events and harmonic distortion levels, since the cause of the problems were unknown.
A disturbance analyzer was installed at the service entrance to determine if voltage variations such as sags or transients were causing the equipment problems. Figure 1 shows an example of disturbance event that was recorded. During the monitoring period, many neutral-to-ground impulses and surges were recorded at the service entrance. No voltage sags or other events were recorded.
Figure 1 – Disturbance Monitoring Results
A spectrum analyzer was also installed at the service entrance to record harmonic distortion levels. Both the voltage and current distortion levels (Figure 2) were very low and should not be causing any equipment problems.
Figure 2 – Harmonic Distortion Results
STUDY METHODOLOGY
Both harmonic distortion and voltage sags have been ruled out as possible causes of equipment problems. Determining the causes of the neutral-to-ground impulses and identifying possible methods to control these impulse levels will probably solve the equipment problems.
SUMMARY
Over the years, vibrations, thermal stresses and building improvements lead to loose connections in wire terminations. On current-carrying conductors, loose connections lead to arcing and sparking and result in high frequency transients. On neutrals, loose connections result in abnormally high or low voltages and result in an unstable reference for highly sensitive electronics.
An infrared heat detector was used to locate loose wiring connections, and once these connections were fixed, the neutral-to-ground voltages disappeared as well as the equipment problems.
REFERENCES
Grounding and Shielding in Facilities, R. Morrison and W. H. Lewis, John Wiley and Sons, Inc., 1990.
RELATED STANDARDS IEEE Standard 1159
GLOSSARY AND ACRONYMS CVT: Constant Voltage Transformer CBEMA: Computer and Business Equipment Manufacturers Association
Published by Tom Key, EPRI PEAC, Knoxville, TN, Email: tkey@epri-peac.com, 2003
Power Quality Case Studies – Understanding compatibility issues DPQ Project – Benchmarking system power quality Advancements in power quality monitoring and managing power quality monitoring information – PQView Tools for power quality analysis – PQ Diagnostic System Power Quality Services – Is it a business or a customer service?
The DPQ Project benchmarked PQ on distribution systems in the US Many utilities followed with extensive benchmarking projects for their individual systems. This continues to be a priority. This also resulted in tools and indices for benchmarking – Reliability Benchmarking Methodology and PQView.
Another way of showing the same data.. This includes durations which are the result of fault clearing times.
Internal facility problems dominate the issues – Wiring and grounding problems, Connections, Internal switching concerns, Load variations and, harmonics affecting the facility voltage Some utility issues – Capacitor switching concerns, Harmonic resonance, Voltage sags and momentary interruptions due to faults, Voltage variations (flicker)
All power quality issues come down to economics. Finding the most cost effective way to solve problems and identifying the investments that are economically justified require a systems approach to the economic analysis. This is a significant area of research – how much do power quality problems cost? How much should utilities invest in improving power quality vs investments from customers in improving immunity?
Many utilities experimented with PQ programs as profit-making service opportunities. For a variety of reasons, most of these did not succeed.
SEMI F47 Provides a template for development of standards that can improve the performance of equipment in critical industries : Utilities, Manufacturers, End Users Now working with other industries to develop similar approaches to improve compatibility.: Automotive initiative is under way right now, Textiles, Hospitals, Plastics, Petrochemical etc.
Standards development is ongoing. The emphasis right now is trying to bring an international perspective to standards. What are the compatibility levels? How should we measure and document PQ? How should limits be applied to equipment, customers, the supply system?
Power quality must be a business. All investments must be justified. Regulations must be developed to support flexibility in implementation of power quality solutions at all levels of the system.
Power quality standards become international PQ Monitoring is everywhere Power quality management becomes part of system operations Planning for power quality Providing flexible levels of power quality to meet customer needs Expert systems to identify problems use power quality monitoring information Power quality MUST be a business
The whole system will be monitored. These systems will be part of systems operation and system maintenance programs. The monitoring systems can be the basis of future premium power service offerings, distributed generation performance, customer system performance, etc. The monitoring systems will integrate equipment for many applications (relays, meters, controls, etc.) Intelligent applications will be built off the voltage and current monitoring.
All power quality parameters that can impact customer and system operation will be tracked continuously. The information will be used as part of overall system performance evaluation and prioritizing expenditures to improve performance.
PQView provided the capability to analyze large volumes of information. PQWeb set the stage for sharing information in the easiest manner – the web.
The opportunity to provide flexible levels of power quality requires innovations in the regulation of utilities and technology implementations to achieve the flexible levels of power quality.
Smart monitoring systems will help us operate the power system, identify problems and fix the problems faster and more efficiently. Fault location, Equipment problems, System efficiency etc.
Quality and Reliability are not POINT values System level indices need to move down to substation/feeder level in a probabilistic framework to better define consumer risk.
Published by Electrotek Concepts, Inc., PQSoft Case Study: PQ Investigation at a Battery Facility, Document ID: PQS0402, Date: March 30, 2004.
Abstract: This case study presents the results of a power quality investigation at a battery manufacturing facility. The facility had been experiencing a high rate of motor failures and was experiencing problems with its computer control system. Ground noise caused by the ungrounded 480 V system and ground loops was part of the problems identified with the computer control system. A ground fault on the 480 V system was found and removed. The installation of harmonic filters reduced the THD from 19% down to 2%. Some of the motor failures were attributed to the basic nature and risks associated with an ungrounded 480 V system.
INTRODUCTION
There are concerns about the power distribution system at a typical Battery Facility. Plant personnel perceive a high failure rate of motors, and problems experienced by the installation of a new system to control battery formation are the most immediate concern. This case study addresses the following issues:
Formation Computer Control
Grounding of the Distribution System
Harmonic Distortion
FORMATION ROOM COMPUTER CONTROL
The computer control for the formation room at the current facility has encountered past operational difficulties. A similar system was installed in a sister plant successfully. The following problems occurred with the new system at the current facility:
Formation room attendants did not trust the system, and a high number of batteries were rejected for improper formation.
Temperature indications, when compared with manual readings, were often in error +/-10 degrees, and sometimes in error by 50 degrees. The errors were intermittent, with no consistent pattern.
Current indications that often read low, causing the rectifier unstable operation.
The problems with the system are due to the following factors:
Lack of ownership for the problem of getting the system corrected. Recently a plant engineer has been added there to address this concern.
Ground noise caused by the ungrounded 480V system.
A shared common reference that becomes distorted by noise.
Inherent lack of accuracy in the Hall Effect sensor boards. Bench tests have shown that under laboratory-type conditions, the best accuracy achievable is on the order of +/-5%.
Electromagnetic interference to the current signals caused by their proximity to the rectifier reactors.
Ground loops, exasperated by the installation of a new driven-ground rod at the UPS powering the wall-mounted computers.
The 30V wiring insulation on the temperature probes failing, and coming into contact with the 300V rectifier circuits. This is in evidence by burned insulation found, and by monitoring which showed a 300V offset (dc) on the ground system.
To date, the following steps have been taken to improve the system:
A ground fault was isolated from the power system.
A recorder was used to check the accuracy of the signals going to the wall computers.
Filter capacitors installed on the Analog Input Boards to the controller, to correct the noise on the current signals.
The driven-ground rod at the UPS was removed from the system.
The temperature probes and their associated shield wires were isolated from the system.
A BMI-8800 Power Disturbance Recorder was installed on the power feed to the wall computers, to monitor for ground noise.
Figure 1 – Powering Arrangements for the Wall Computers
Figure 1 shows how the wall computers are powered. The system lacks a ground reference point — a single point where all ground wires are connected from. The system would be improved by powering each wall computer from a dedicated circuit, each with an individual ground connection. The improved system would have ground connections run with separate wires that are all tied to a common reference point inside the breaker panel. The common reference point would be a ground bus designed for such a purpose (often a 1/4” copper plate is used).
Figure 2 – Current Sensor Board with Shared Signal Return
Figure 2 depicts the current sensor board. The board is used for eight Hall Effect transducers to monitor the current of eight circuits. The board is designed with a signal common for all the signal transducers. Bench tests indicate that the transducers appear to be accurate within 0.5%. However, those tests show that the signal common causes the reference to be corrupted, such that the accuracy of this board is only within about 5%, and the errors are not consistent.
An improved design of this board would have separate commons for all of the eight signals. Twisted-pair, shielded cable would offer the best immunity for electromagnetic and electric field interference. The shield of the cable should be grounded at both ends, to ensure the integrity of an alternative path (rather than through the signal conductors) for electromagnetic interference. The shield of the cable should be tied to the grounding of enclosures, etc., and not to the logic common. Where possible, the logic common of the system should be isolated from the safety grounding system.
Table 1 – Measurements Taken with a Fluke 41 Hand-held Harmonics Meter
11:00 AM
1:00PM
5:20PM
6:30PM
UPS Input Voltage
240V 2%THD
236V 1.8%THD
234V 2.2%THD
UPS Input Voltage (L-Ns)
117.8/117.8
118/118
117.2/117.2
UPS Output Voltage
235V 0.7%THD
235V 3.2%THD
235V 6.5%THD
UPS Output Voltage (L-Ns)
111.5/121.6
115/119
116.3/118.3
Common-Earth Voltage
0.1V
0.0V
0.1V
Ground Wire to Transformer Ground Current
0.16A 40%THD
0.16A 29%THD
0.18A 27%THD
0.18A 26%THD
Ground Wire to UPS (1) Ground Current
0.16A 33%THD
0.19A 30%THD
0.20A
0.19A 25%THD
Ground Wire to UPS (2) Ground Current
0.19A 23%THD
0.2A 24%THD
0.26A 40%THD
0.27A 40%THD
Ground Wire to Wall Units Ground Current
0.07A
0.08A
0.14A
0.14A 35%THD
UPS Input Current
3.11A 6.5%THD
3.85A 6.9%THD
6.12A 12%THD
6.12A 12%THD
UPS Output Current
0.05A
2.0A 120%THD
5.64A 101%THD
5.62A 100%THD
The measurements in Table 1 were taken with the system in an isolated state. The high amount of harmonic distortion in the UPS output current is normal for computer switch mode power supplies. The amount of harmonic distortion in the ground currents is indicative of zero sequence (chiefly third harmonic) frequencies present — and also is not unusual. In general, the currents flowing through the grounding system were seen to be negligible. These measurements were taken after the ground rod was disconnected from the system. If the ground rod were reconnected to the system, it is possible it would attract other fault current from the plant, generating more noise on the signal reference.
Should difficulties arise in the future, the currents in the ground wires should be checked. The values in Table 1 provide a reference. For example, if the temperature probes are reconnected, it is possible a fault in one of them could cause ground current to flow, and a noisy data reference. Such a problem might be discovered by a relatively high amount of current flowing through the ground wires.
Figure 3 – Power Disturbance Analyzer Connections
A BMI power disturbance analyzer was connected to the system as shown in Figure 3. The purpose of this connection was to determine if there was noise on power (channels 1-2) and the data common signal (channels 3-4). Also the analyzer provides “time stamping” of any disturbances that might be correlated with any operation difficulties of the system.
Table 2 summarizes some of the early results from the disturbance analyzer. The levels recorded should be considered normal. It is important to note that the signal common-to-earth voltage remained at a very low level. Should a ground fault interfere with the signal common, this should show up on this measurement.
Table 2 – Power Disturbance Analyzer Measurement Results
Feb 1 5:00-6:00 pm
Feb 1 6:00-7:00PM
Feb 2 9:00-12:00Noon
UPS IN 240 RMS Noise
228.1-235.9V 0.0-0.9Vpk
227.6-234.9V 0.1-0.9Vpk
229-233.9V 0.1-0.2Vpk
UPS OUT 240 RMS Noise
229.5-236.4V 0.1-1.8Vpk
230.0-236.4V 0.1-0.9Vpk
233.3-234.8V 0.1-0.1Vpk
UPS OUT 120 RMS Noise
114.5-117.4V 0.1-1.0Vpk
113.8-117.2V 0.1-0.9Vpk
115.7-116.2V 2.7-3.1Vpk
Common-Earth RMS Noise
0.0-0.2V 0.3-1.1Vpk
0.1-0.2V 0.3-0.9Vpk
0.0-0.1V 0.1-0.2Vpk
HARMONICS
During the shutdown of Thanksgiving 1993, harmonic filter capacitors were installed on the 480V mains. Currently the harmonic distortion typically found in the plant is about 2% THD, which is well within the IEEE Standard 519 recommended guideline of 5%.
Prior to the installation of the filters, the harmonic distortion on the system was reported to be as high as 19%, dominated by the 5th harmonic frequency. These conditions were clearly caused by the Bitrode rectifiers in combination with the power factor correction. The power factor correction is required for voltage support. The Bitrode rectifiers are a six-pulse design, which would be expected to generate high amounts of 5th, 7th, 11th, and 13th harmonic frequencies. These past conditions would have exceeded the amount of harmonic voltage distortion (generally thought to be around 10% THD) that can cause electric motors to run at higher temperatures, and may have weakened the insulation of some of the motors at the facility.
UNGROUNDED DISTRIBUTION SYSTEM
The system at the Plant utilizes a 480V, three-wire ungrounded power system. Although the system is intentionally ungrounded, a reference to ground normally exists due to distributed capacitance between the phases and ground, and also due to the presence of the ground detection lights. Normally, this will allow each phase to be 277V above ground. When one phase of the three-wire system comes into contact with ground, while some capacitive charging current may flow, there is no substantial fault current. This condition causes one of the phases becomes grounded, while the other phases rise to 480V above ground. Additionally, this condition can also lead to an arcing ground fault, which has the potential to cause damaging overvoltage conditions.
Several of the drawbacks of ungrounded power systems are described in the book, Industrial Power Systems Handbook, edited by Donald Beeman, 1955 McGraw-Hill. In one particular instance cited in the book, a plant failed 40-50 motors during a two-hour period due to an arcing fault. In that instance a test instrument revealed voltages above 1200V phase-to-ground on a 480-volt system.
The ANSI/IEEE Std 141-1993 Recommended Practice for Electric Power Distribution for Industrial Plants makes the following statements (page 365):
“It is generally conceded that this practice (ungrounded systems) introduces potential hazards to insulation in apparatus supplied from the ungrounded system.”
“Because of the capacitance coupling to ground, the ungrounded system is subject to dangerous overvoltages (five times normal or more) as a result of an intermittent contact ground fault (arcing fault) or a high inductive reactance connected from phase to ground or phase to phase”
Accumulated operating experience indicates that, in general-purpose industrial power distribution systems, the overvoltage incidents associated with ungrounded operation diminish the useful life of insulation in such a way that electric circuit and machine failures occur more frequently than they do on grounded systems.”
It is possible to ground the 480-volt power system. Since the 480-volt system originates at a single bus in the substation, it would be possible to apply a single grounding transformer there. The required size of the grounding transformer would be approximately one-tenth the size of the overall transformer supply. However, ground fault protection would also be required at the switchgear, at a cost which has been estimated to be around $100,000.
The building schematics show the existing switchgear connected to a ground grid, while the new switchgear panel in the substation is connected to separate earth electrodes. Improved lightning performance would result from bonding both earth connections together. One method of doing this would be to ensure they are both connected to the ground grid.
The 300-volt dc circuits for the battery formation process are also ungrounded. However, none of the potential overvoltage situations possible with the ac system exist with the dc system. The ungrounded dc system has the support of years of operating without serious injury to personnel, and should be continued.
SUMMARY
The difficulties with the formation computer system are primarily due to the following factors:
Lack of electrical isolation between the input sensors (temperature and current)
Noise on the grounding system due to arcing faults.
Inherent inaccuracies present in the original design.
Grounding of the reference signals that does not originate at a “single point.”
The following measures have already been undertaken to improve the performance of the formation computer controls:
The signals from the current sensors are filtered.
A ground fault removed from the power system
The temperature probes are isolated from the system.
The driven ground rod at the UPS has been eliminated
Specific recommendations to consider for improvement of the formation control system:
Run a separate power circuit and ground wire to each process computer. Have each of the 12 ground wires connected to a common ground bus (1/4” copper plate or similar) and make sure this ground bus is tied to building steel, and to the ground lug at the 480V bus duct.
Tie the shield (of the cable from the current sensor board) to ground at both ends. This will restore the electromagnetic shielding. Do not connect it directly to data common. Assure it has good contact with building steel, via conduit, etc.
Although the ungrounded power system causes some overvoltage conditions that occasionally cause motors to fail, it is probably not justifiable to expend $50-100k to change it. The harmonic distortion levels at the plant are currently acceptable.
REFERENCES
Industrial Power Systems Handbook, edited by Donald Beeman, 1955 McGraw-Hill.
RELATED STANDARDS IEEE Standard 519 ANSI/IEEE Standard 141-1993 Recommended Practice for Electric Power Distribution for Industrial Plants
GLOSSARY AND ACRONYMS IEEE: Institute of Electrical and Electronics Engineers THD: Total Harmonic Distortion