Major Health Care Center

Published by Dranetz – BMI Case Studies


Severe power quality problems damaged X-ray equipment, costing $100,000 in one instance. The source of the problem was the switch over from utility to generator power, during regular testing and emergency situations. Figure 1(below) identified the cause of the problem, an out-of-phase transfer, captured by On Power with a Dranetz 658 Analyzer.

Major Health Care Center figure1
Figure 1

Ideally, an online UPS represents the best solution when protecting against low frequency / high energy events such as out-of-phase transfers (capacitor bank switching represent similar problems). The challenge was dealing with the size and shape of the inrush currents the X-ray demands as it cycles through its program (See Figure 2). Not only did current rise from 20 Amps to 100 Amps (380V system), but even harmonics with a THD of 65% were present. The added challenge was that this X-ray procedure represented “invasive” techniques as catheters are inserted into arteries, sometimes into the heart.

 

Major Health Care Center figure2
Figure 2

On power solution was based on four phases:

  1. Extensive X-ray system monitoring
  2. Solution research/simulation
  3. Post system installation monitoring
  4. Permanently installed Power Quality Monitoring with communication ability. By injecting current to compensate for the distorted waveform, the AIM Filter not only improves the quality of power to the X-ray, it lowers the stress on the UPS, lowers impedance placed on the system by the UPS, and improves the output THD to the rest of the systems distribution (See Figure 3).
Major Health Care Center figure3
Figure 3

Published by PQBlog

Electrical Engineer

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s